LR Tech Park Progress Report #7

417 Building

First Floor
The contractor has demoed out the floor slab at the coffee bar. The plumber has completed the new rough-in and the contractor is grading back and placing the fill and ready to pour the slab back. Metal stud work continues on first floor.

Upper Floors
Tape and float; sanding of sheetrock continues. The contractor is ready to start primer on the walls. The pipe insulation continues. Duct insulation continues. The electrician continues running conduit and pulling wire and installing boxes. Can lights continue in the sheetrock ceilings. Sprinkler piping continues.

415 Building

Demo continues of the interior stair and steel supports in preparation for the installation of the fire stair.